Analysis of the productivity value of hebel couple's work using work study method in building construction project pilot scale product development facility
##plugins.themes.academic_pro.article.main##
Abstract
Construction is a field in the world of property in the part of planning and construction involving architects and civil engineering. Project is a complex activity and has a nature that cannot occur repeatedly, has a limited time using certain resources with the aim of producing a product. One aspect of a successful construction project is resources. This study uses the work study method, namely taking direct observation data in the field by comparing the work group that has been created with the 2008 SNI rules for working on 1 m2 of hebel installation work. The result of this study is that the group that has the highest productivity value is work group 3 because the average volume produced is large compared to other groups. The most efficient working group is group 2 because with not too high costs it can produce an average volume of 15.6875 m2 per day. The total wage paid for hebel wall installation work per 1 m2 of work group 1 amounted to Rp 126,329.00. Group 3 (productive) amounted to Rp 183,166.00. Wages for work group 2 (efficient) amounted to Rp 166,467.00. Working group 2 is the most optimal working group. The volume of work that can be produced by the working group is 15.6875 m2 hebel pairs in 1 working day.
##plugins.themes.academic_pro.article.details##
References
Andardi, F. R. (2019). Studi Pekerjaan Plesteran, Acian, dan Pengecetan Berdasarkan Produktivitas Jumlah Tenaga Kerja dengan Metode Work Study.
Andriani, Astri Dwi and Mulyana, A. and W. (2022). Manajemen sumber daya manusia. TOHAR MEDIA.
Andris, Juergen Bonihasian Joshua K and Nursin, A. (2020). Analisis Produktivitas Tenaga Kerja Pekerjaan Dinding Bata Ringan. Prosiding Seminar Nasional Teknik Sipil, 18–23.
Anwar, Hasmita and Adil, Adil and Suardi, A. (2023). Pengaruh Keselamatan Dan Kesehatan Kerja Terhadap Produktivitas Kerja Karyawan Pada PT. Bumi Mineral Sulawesi. SEIKO: Journal of Management & Business, 6(1), 536–544.
Asmaroni, Dedy and Sesaria, S. (2022). Analisis Produktivitas Tenaga Kerja Pada Pekerjaan Pagar Menggunakan Metode Time Study Pada Pembangunan Kantor \& Gudang Djarum Dso (Distric Sales Office) Pamekasan. Rekayasa: Jurnal Teknik Sipil, 6(2), 1–6.
Belladona, Meilani and Antoro, Edito Dwi and Sandra, A. (2019). Analisis Produktivitas Tenaga Kerja Pada Pekerjaan Beton Bertulang Menggunakan Metode Time Study.
Darmanto, Budi and Widjayakusuma, Jack and Simanjuntak, M. (2020). Identifikasi Faktor-Faktor yang Menyebabkan Cost Overrun pada Konstruksi Gedung Bertingkat. Seminar Nasional Teknik Sipil X 2020.
Gunawan, Agus and Setyawan, A. (2022). Analisis Produktivitas Hasil Pekerjaan Konstruksi Antara Kerja Normal dan Kerja Lembur. Surakarta Civil Engineering Review (SCER), 2(1), 49–61.
Hakiki, Moh Saiful and Angelia, Tisa and Widiwati, C. S. (2022). STANDAR OPERASIONAL PROSEDUR (SOP) SISTEM PELAPORAN KINERJA SDM PADA PROYEK DESAIN ARSITEKTUR DALAM KAITANNYA DENGAN DISIPLIN KERJA1. Pawon: Jurnal Arsitektur, 6(2), 37–54.
Hakim, R. R. (2019). Terminal Penumpang Pelabuhan Luwu Timur di Kabupaten Luwu Timur dengan Pendekatan Arsitektur Hemat Energi. Fakultas Sains dan Teknologi.
Hanifah, U. (2019). Transformasi sosial masyarakat Samin di Bojonegoro (Analisis perubahan sosial dalam pembagian kerja dan solidaritas sosial Emile Durkheim). Jurnal Sosiologi Agama, 13(1), 41–71.
Hernandi, Yodie and Tamtana, J. S. (2020). Faktor-Faktor Yang Mempengaruhi Produktivitas Pekerja Pada Pelaksanaan Konstruksi Gedung Bertingkat. JMTS: Jurnal Mitra Teknik Sipil, 299–312.
Kahn, Matthew E and Li, P. (2019). The effect of pollution and heat on high skill public sector worker productivity in China. National Bureau of Economic Research.
Kartika, Nia and Robial, Siti Muawanah and Pratama, A. (2021). Analisis produktivitas tenaga kerja pada pekerjaan kolom di proyek pembangunan gedung Pemda Kabupaten Sukabumi. Jurnal Momen Teknik Sipil, 3(2), 103–112.
Pramana, D. (2020). Pengaruh Tata Ruang Kantor Terhadap Produktivitas Kerja Pegawai Pada Kantor Dinas Kesehatan Daerah Kabupaten Tapanuli Selatan. Jurnal Administrasi Dan Perkantoran Modern, 9(2).
Pratristyo, H. L. (2020). ANALISA PERBANDINGAN PRODUKTIVITAS DAN HARGA SATUAN PEKERJAAN PEMASANGAN LANTAI KERAMIK PADA ANALISA LAPANGAN DENGAN SNI. Universitas Islam Indonesia.
Prawirosentono, Suyadi and Primasari, D. (2022). Manajemen Stratejik & Pengambilan Keputusan Korporasi (Strategic Management & Corporate Decision Making). Bumi Aksara.
Puraro, Elis Rosalin and Iskandar, T. (2019). Analisis Perbandingan Koefisien Upah Kerja dan Bahan Pekerjaan Dinding Bata Ringan antara Aktualisasi dan SNI 2016. Student Journal Gelagar, 1(1), 15–23.
Reza, Ryan Restu and Santoso, A. (2022). Penerapan Lean Manufacturing di Sebuah Perusahaan Keramik. Jurnal Teknik Industri: Jurnal Hasil Penelitian Dan Karya Ilmiah Dalam Bidang Teknik Industri, 8(2), 140–149.
Saputra, Akhmad Andi and Nugroho, Dandy and Sukmana, F. (2020). Perbandingan Estimasi Anggaran Biaya Antara Harga SNI Dengan Harga Kontraktor Pada Proyek Pembangunan Pagar di Kandangan Surabaya. Wahana Teknik, 9(1), 21–29.
Sarosa, S. (2021). Analisis Data Penelitian Kualitatif. Pt Kanisius.
Sigit, A. (2020). Perbandingan Produktivitas Pekerjaan Pasangan Dinding Bata Ringan dan Bata Merah. Universitas Islam Indonesia.
Sutihermi. (2022). Implementasi Model Pembelajaran Kooperatif Team Accelerated Instruction Untuk Meningkatkan Hasil Belajar Akuntansi Pada Kompetensi Dasar Menjelaskan Tahap-Tahap Proses Pencatatan Transaksi Perusahaan Jasa Siswa Kelas X Ak. 2 SMK Negeri 1 Dumai Tahun Ajara. Jurnal Ilmiah Wahana Pendidikan, 8(21), 638–647.
Tunjungsari, Hetty Karunia and Ginting, G. (2020). Perkembangan Dunia Usaha di Era Digital. Pustaka. Ut. Ac. Id.
Wardani, L. A. P. (2021). ANALISA PERBANDINGAN BIAYA DAN WAKTU DALAM PENGGUNAAN MATERIAL PRECAST DAN BATA RINGAN PADA PEKERJAAN DINDING LUAR (Studi Kasus: Proyek Apartemen Barsa City, Depok, Sleman, Yogyakarta). Universitas Atma Jaya Yogyakarta.
Wijaya, F. A. (2022). Analisis Produktivitas Tenaga Kerja Konstruksi Pada Pekerjaan Pemasangan Keramik Menggunakan Mpdm (Method Productivity Delay Model)(Studi Kasus Proyek Pembangunan Masjid Muhammadyah Boarding School Kabupaten Lombok Barat, Narmada, Ntb). Universitas Islam Indonesia.
Wiratama, P. G. A. U. (2022). ANALISIS PERBANDINGAN PRODUKTIVITAS TENAGA KERJA RENCANA DENGAN PRODUKTIVITAS PELAKSANAAN PEKERJAAN KONSTRUKSI PROYEK PEMBANGUNAN GEDUNG PENGADILAN NEGERI BADUNG. Universitas Mahasaraswati Denpasar.