Time efficiency analysis of single floor shophouse construction project using the CPM (Critical Part Method)

##plugins.themes.academic_pro.article.main##

Surahman Surahman
Yosafat Henry Radityatama
Ahmad Padillah
Satryawati Satryawati

Abstract

This study examines the efficiency of the implementation time of a single floor shophouse construction project in Samarinda City, through the application of the Critical Path Method (CPM). Secondary data in the form of a project implementation schedule was analyzed by preparing a work network diagram, calculating Earliest Event Time (EET) and Latest Event Time (LET), and identifying the critical path. The results of the analysis show that the duration of project implementation with normal time reaches 121 days, while with an accelerated scenario (quick time) can be cut to 87 days. The critical path consists of the sequence of activities A (preparation) → B (foundation) → C (structure) → D (wall) → E (roof) → G (harmonica door) → H (bathroom) → I (septic tank) → J (canopy) → K (electrical installation) → L (painting) → M (finishing), so that these activities become the main focus of control to avoid delays. Strategic recommendations include optimizing resource allocation, rescheduling non-critical activities, and implementing fast-track and overlapping work to shorten the implementation duration without compromising construction quality

##plugins.themes.academic_pro.article.details##

How to Cite
Surahman, S., Radityatama, Y. H., Padillah, A., & Satryawati, S. (2025). Time efficiency analysis of single floor shophouse construction project using the CPM (Critical Part Method). Enrichment : Journal of Management, 15(2), 92-100. https://doi.org/10.35335/enrichment.v15i2.2266

References

Abdurrasyid, Luqman, Abdul Haris, dan Indrianto. 2019. “Implementasi Metode PERT dan CPM pada Sistem Informasi Manajemen Proyek Pembangunan Kapal.” 5(1). doi:(https://doi.org/10.23917/khif.v5i1.7066).
Alawiyah, Tuti, Yani Sri Mulyani, Muhammad Azhar Gunawan, Rizqi Setiaji, dan Hari Nurdin. 2022. “Sistem Informasi Manajemen Proyek (SIMAPRO) Berbasis Web (Studi Kasus: PT. Arya Bakti Saluyu).” Jurnal Khatulistiwa Informatika 10(2):129–35. doi:10.31294/jki.v10i2.14061.
Altatri, Defatia. 2021. “Program Studi Perencanaan Wilayah Dan Kota Fakultas Teknik Universitas Islam Riau Pekanbaru 2022.” doi:http://repository.uir.ac.id/id/eprint/11049.
Arief, M., dan Y. Latief. 2021. “Project Planning System Improvement in Residential Development Project: A Risk Analysis.” IOP Conference Series: Materials Science and Engineering 1098(2):022032. doi:10.1088/1757-899X/1098/2/022032.
Bank Indonesia. 2024.“Perkembangan Properti Komersial (PPKOM).” https://www.bi.go.id/id/publikasi/laporan/Pages/PPKom_Triwulan_I_2024.aspx.
Brege, Staffan, Stehn ,Lars, dan Tomas and Nord. 2014. “Business models in industrialized building of multi-storey houses.” Construction Management and Economics 32(1–2):208–26. doi:10.1080/01446193.2013.840734.
Darsana, I. Made, Luluk Tri Harinie, Frankie Jan Salean, Siti Nurmayanti, Dion Eko Prihandono, Nurul Aziza, Susriyanti, Hendrato Setiabudi Nurgroho, dan Heriasman. 2024. Manajemen Proyek.
Di Maddaloni, Francesco, dan Kate Davis. 2017. “The influence of local community stakeholders in megaprojects: Rethinking their inclusiveness to improve project performance.” International journal of project management 35(8):1537–56.
Dinda Ayu Devi, Dinda, Dafid Irawan, dan Muhammad Cakrawala. 2022. “Analisas Percepatan Waktu Terhadap Biaya Dengan Sistem Shirt Menggunakan Precedence Diagram Method, Fast-Track dan Critical Path Method.” BOUWPLANK Jurnal Ilmiah Teknik Sipil dan Lingkungan 1(2):21–30. doi:10.31328/bouwplank.v1i2.220.
Effendy, Faried, dan Barry Nuqoba. 2017. “Sistem Monitoring Online untuk Perusahaan Multi Cabang.” ProTekInfo(Pengembangan Riset dan Observasi Teknik Informatika) 3:55–59. doi:10.30656/protekinfo.v3i0.59.
Ellram, Lisa M., dan Wendy L. Tate. 2016. “The Use of Secondary Data in Purchasing and Supply Management (P/SM) Research.” Journal of Purchasing and Supply Management 22(4):250–54. doi:10.1016/j.pursup.2016.08.005.
Emanuelson, Ulf, dan Agneta Egenvall. 2014. “The data–Sources and validation.” Preventive veterinary medicine 113(3):298–303.
Fazis, Muhammad. 2022. “Perencanaan Proyek dan Penjadwalan Proyek.” doi:(https://doi.org/10.59188/jurnalsostech.v2i12.517).
Ferdous, Wahid, Yu Bai, Tuan Duc Ngo, Allan Manalo, dan Priyan Mendis. 2019. “New advancements, challenges and opportunities of multi-storey modular buildings – A state-of-the-art review.” Engineering Structures 183:883–93. doi:10.1016/j.engstruct.2019.01.061.
Haryani, Dwi Septi, Surya Kusumah, Betty Leindarita, Hasnarika, dan Armansyah. 2024. Riset Operasi.
Huo, Xiaosen, Hao Xue, dan Liudan Jiao. 2023. “Manajemen risiko proyek perbaikan kawasan permukiman lama dalam rangka pembangunan hijau.” doi:https://doi.org/10.1016/j.enbuild.2022.112708.
Hurst, David, Sharon Sharpe, dan Valerie A. Yeager. 2017. “Administrative preparedness strategies: expediting procurement and contracting cycle times during an emergency.” Public Health Reports 132(3):294–97.
Julkarnaen, Tubagus Irwan, dan Lely Herlina. 2015. “Analisa Perbaikan Penjadwalan Perakitan Panel Listrik Dengan Metode CPM dan PERT (Studi Kasus : PT. Mega Karya Engineering).” doi:(https://dx.doi.org/10.36055/jti.v3i1.347).
Lis, Kartini, Abdullah, Juli Riauwati, Yoeliastuti, Hendy Tannady, Khasanah, Hade Chandra Batubara, Haryati La Kamisi, Wendy Liana, dan Yuli Purbaningsih. 2024. Manajemen Proyek. Cendikia Mulia Mandiri.
Mahadik, Sunil, dan Vinay Topkar. 2023. “Validity and reliability testing of the questionnaire used to finalize criteria for the evaluation of the contractor’s performance.” Archives of Civil Engineering 477–92.
Mar’aini, Mar’aini, dan Y. Rahmat Akbar. 2022. “Penentuan Jalur Kritis untuk Manajemen Proyek (Studi Kasus Pembangunan Jalan Selensen-Kota Baru-Bagan Jaya).” Jurnal Pustaka Manajemen (Pusat Akses Kajian Manajemen) 2(1):6–13. doi:10.55382/jurnalpustakamanajemen.v2i1.184.
Megawati, Andi, dan Dian Gustina. 2018. “Membangun Sistem Informasi Monitoring Kegiatan Proyek Pemancar Sinyal BTS Berbasis Web Pada PT. Swatama Mega Teknik.” doi:https://dx.doi.org/10.22441/fifo.2018.v10i1.003).
Messah, Yunita Afliana. 2013. “Kajian Penyebab Keterlambatan Pelaksanaan Proyek Kontrusi Gedung di Kota Kupang.” Jurnal Teknik Sipil (2). doi:(https://doi.org/10.35508/jts.2.2.157-168).
Odedairo, Babatunde Omoniyi. 2024. “Assessing the Influence of Various Work Breakdown Structures on Project Completion Time.” Engineering, Technology & Applied Science Research 14(2):13773–79. doi:10.48084/etasr.7023.
Purwanto, Anim. 2022. Konsep Dasar Penelitian Kualitatif Teori dan Contoh Praktis. Pusat Pengembangan Pendidikan dan Penelitian Indonesia.
Sayyid, Walid Musatafa Al, dan Safaaaldeen Hussein Ali. 2021. “Strategi Manajemen Proyek Terpadu - Studi Kasus Investasi Perumahan.” doi:https://doi.org/10.1109/ICASEA53739.2021.9733070.
Setiawan, Edi. 2019. “Manajemen proyek Sistem Informasi Penggajian Berbasis Web.” Jurnal Teknik 17(2):84–93. doi:10.37031/jt.v17i2.50.
Sinurat, Febrian, dan Felly Misdalena. 2024. “Analisis Manajemen Proyek Dengan Metode Critical Path Method (CPM) Pada Proyek Pembangunan Gedung Chandra Tanjung Karang.” Jurnal Konstruksi 22(2):98–107. doi:10.33364/konstruksi/v.22-2.2131.
Surahman, Angga Kusumah, dan Rindayani S. Tomby. 2024. “Project Management Planning of the Small House Construction in Samarinda Using the Critical Path Method (CPM).” (3). doi:(https://doi.org/10.35335/enrichment.v14i3.1939).
Thomas, H. Randolph. 2000. “Schedule acceleration, work flow, and labor productivity.” Journal of Construction Engineering and Management 126(4):261–67.
Waruwu, Marinu. 2024. “Pendekatan Penelitian Kualitatif: Konsep, Prosedur, Kelebihan dan Peran di Bidang Pendidikan.” Afeksi: Jurnal Penelitian dan Evaluasi Pendidikan 5(2):198–211. doi:10.59698/afeksi.v5i2.236.
Widhiawati, I. A. Rai. 2009. “Analisi Faktor-faktor Penyembab Keterlibatan Pelaksanaan Proyek Konstruksi.” 8. doi:(https://doi.org/10.33559/err.v2i2.1715).

Most read articles by the same author(s)