Critical path analysis scheduling project with critical path method (CPM) using application microsoft project on type 78 house construction project

##plugins.themes.academic_pro.article.main##

Suramli Suramli
Karenina Aulia Rachman
Nanda Fitria Dewi
Dea Salsa Novianda
Surahman Surahman

Abstract

This study presented the scheduling of a Type 78 house construction project using the Critical Path Method implemented in Microsoft Project. The research defined and sequenced all construction activities, estimated their durations based on field data, and modeled the schedule within the software. The CPM analysis revealed a total project duration of 120 days, with site preparation, structural framing, and roofing installation identified as the critical path activities. Non-critical tasks were found to have total floats of up to 15 days, indicating opportunities for resource reallocation and schedule compression. By simulating task overlaps and adjusting resource assignments, the study demonstrated a potential reduction in overall completion time by approximately 10%. The results confirmed that applying the Critical Path Method in Microsoft Project enhanced schedule visibility, facilitated proactive delay management, and provided practical guidance for optimizing residential construction timelines.

##plugins.themes.academic_pro.article.details##

How to Cite
Suramli, S., Rachman, K. A., Dewi, N. F., Novianda, D. S., & Surahman, S. (2025). Critical path analysis scheduling project with critical path method (CPM) using application microsoft project on type 78 house construction project. Enrichment : Journal of Management, 15(2), 73-81. https://doi.org/10.35335/enrichment.v15i2.2263

References

A. Levis, Delay Construction. Langford: Cahner Books Internasional, 1996.
Avlijas, G. (2018). Examining the Value of Monte Carlo Simulation for Project Time Management. Management:Journal of Sustainable Business and Management Solutions in Emerging Economies, 24(1), 11. https://doi.org/10.7595/management.fon.2018.0004
BPS. (2023). Jumlah Penduduk Pertengahan Tahun (Ribu Jiwa), 2022–2024. Retrieved from https://www.bps.go.id/id/statistics-table/2/MTk3NSMy/jumlah-penduduk-pertengahan-tahun--ribu-jiwa-.html
Dewi, C. P., Anton, E., & Alwi, S. (2016). Perhitungan Rencana Anggaran Biaya dan Waktu Pelaksanaan Pekerjaan pada Pembangunan Gedung Serbaguna di Jalan Bung Tomo Samarinda Kalimantan Timur. Jurnal Inersia, VIII.
DIPS42. (2024, October). Accurate Data in Construction - The Importance. Https://Www.Dibs42.Com/Blog/Accurate-Data-in-Construction-the-Importance.
Dwi Akbar, M., Alfiyah, S., Kiai, N., Achmad, H., & Jember, S. (2024). Analisis Manajemen Kontruksi Pada Proyek Pembangunan Gedung Pondok Pesantren Mambaul Ulum Pada PT. Rajendra. Jurnal Multidisiplin Ilmu, 2(3), 104–109. https://doi.org/10.59435/gjmi.v2i3.394
Er Kara, M., Ghadge, A., & Bititci, U. S. (2020). Modelling the Impact of Climate Change Risk on Supply Chain Performance. International Journal of Production Research, 59(24), 7317–7335. https://doi.org/10.1080/00207543.2020.1849844
Fadlah, N. N. (2025, April 22). Tunjukkan Tren Positif, Rumah Tapak Dominasi Permintaan Hunian di Samarinda. Https://Www.Rumah123.Com/Panduan-Properti/Tunjukkan-Tren-Positif-Rumah-Tapak-Dominasi-Permintaan-Hunian-Di-Samarinda/.
Fazis, M., & Tugiah. (2022). Perencanaan Proyek dan Penjadwalan Proyek. 2. https://doi.org/https://doi.org/10.59188/jurnalsostech.v2i12.517
F. N. Wowor et al., “Aplikasi Microsoft Project Dalam Pengendalian,” J. Tek. Sipil,vol. 1, no. 8, pp. 543–548, 2013.
Franciko, V. (2025, January 24). Harga Properti di Samarinda Semakin Meningkat: Peluang dan Tantangan bagi Investor dan Pembeli. Https://Www.Rainrealty.Co.Id/Harga-Properti-Di-Samarinda-Semakin-Meningkat-Peluang-Dan-Tantangan-Bagi-Investor-Dan-Pembeli/.
Heizer, J., Render, B., & Munson, C. (2020). Operations Management : Sustainability and Supply Chain Management (13th ed.). Pearson.
K. Dimyati, A. Hamdan., Nurjaman, Manajemen Proyek, Cet. 1. Bandung: CV. Pustaka Setia, 2014.
Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling (12th ed.). John Wiley & Sons, Inc.
La Ode, A., Syarif, M., Purnama, H., Masdiana, Latupeirissa, J. E., Gusty, S., . . . Pagoray, G. L. (2023). Manajemen Proyek Konstruksi. (M. N. La Ola, Ed.) CV Tohar Media.
Lorko, M., Servátka, M., Servátka, & Zhang, L. (2019). How to Improve the Accuracy of Project Schedules? The Effect of Project Specification and Historical Information on Duration Estimates.
Mar’aini, & Akbar, Y. R. (2022). Penentuan Jalur Kritis untuk Manajemen Proyek (Studi Kasus Pembangunan Jalan Selensen- Kota Baru- Bagan Jaya). Jurnal Pustaka Manajemen, 2.
Merwe, L. van der. (2016, June 22). Project Management: Top 10 Tips for Validating your Project Schedule. Https://Www.Virtualprojectconsulting.Com/Project-Management-Top-10-Tips-for-Validating-Your-Project-Schedule/.
Muin, O. E. A. (2022). Analisis Jalur Kritis Penjadwalan Proyek Dengan Metode Critical Path Method (CPM) Menggunakan Aplikasi Microsoft Project Pada Masa Pandemi Covid-19 (Studi Kasus Pembangunan Gedung Kuliah Universitas Muhammadiyah Lamongan). Jurnal Extrapolasi, 19.
Mulyana, A. (2019). Manajemen Proyek Konstruksi. Jakarta: Salemba Empat.
N. Saputra, E. Handayani, and A. Dwiretnani, “Analisa Penjadwalan Proyek dengan Metode Critical Path Method (CPM) Studi Kasus Pembangunan Gedung Rawat Inap RSUD Abdul Manap Kota Jambi,” J. Talent. Sipil, vol. 4, no. 1, p. 44, 2021, doi: 10.33087/talentasipil.v4i1.48.
Ode, A. T. La, Syarif, M., Purnama, H., Masdiana, Latupeirissa, J. E., Gusty, S., Putri, T. S., Latif, F., Dzakir, L. O., Wiriantari, F., & Pagoray, G. L. (2023). Manajemen Proyek Konstruksi (M. N. La Ola, Ed.). CV. Tohar Media. https://toharmedia.co.id
Oetomo, Wateno., 2014. Manajemen Proyek dan Konstruksi dalam Organisasi Kontemporer Bagian II. Penerbit PT. Meditama Sapta Karya. Yayasan Badan Penerbit Pekerjaan Umum, Jakarta
Park, J. (2024). Best Practices for Microsoft Project, Part 1. Https://Mpug.Com/Best-Practices-for-Microsoft-Project-Part-1/.
Prasetiya, K. B., Patriadi, A., & Sajiyo. (2025). Analysis of Time Control Strategies Using The Critical Path Method (CPM) In The Development of The Java Residence Cluster For Mass-Product Housing. 6(1).
Pratasik, F., Malingkas, G. Y., Arsjad, T. T., & Tarore, H. (2013). Menganalisis Sensitivitas Keterlambatan Durasi Proyek dengan Metode CPM (Studi Kasus : Perumahan Puri Kelapa Gading). Jurnal Sipil Statik, 1(9), 603–607.
Putri, F. D., & Ardan, M. (2023). Analisa Penerapan Manajemen Waktu Pada Proyek Pembangunan Bendungan Lau Simeme. INERSIA, 15.
Riyanto, S. (2020). Analisis Penerapan Metode CPM dan PERT pada Proyek Konstruksi. Jurnal Teknik Sipil, 12(1), 45-57.
Saputra, I. H., Erina, Y., & Rodhi, N. N. (2024). Analisis Pengendalian Waktu dan Biaya Proyek Konstruksi dengan Metode CPM (Critical Path Method ). 4. https://j-innovative.org/index.php/Innovative/article/view/17179/11653
Sasongko Nurhuda, D., Sutrisno, W., Langga, D., & Galuh, C. (n.d.). Analisis Risiko Keterlambatan Waktu Pada Pelaksanaan Proyek Pembangunan SPBU (Studi Kasus di Kabupaten Bantul, Yogyakarta).
Soeharto, I. (1999). Manajemen Proyek (Dari Konseptual Sampai Operasional) (Kedua). Erlangga. https://nawindah.files.wordpress.com/2016/05/e-book-manajemen-proyek.pdf
Suhendar, E., & Ulfa, S. (2021). Implementasi Metode Critical Path Method Pada Proyek Synthesis Residence Kemang. 3. https://journal.lppmunindra.ac.id/index.php/JOTI/article/view/4167/3828
Surahman, Kusumah, A., Tiara, Tomby, R. S., & Nurmaulida. (2024). Project Management Planning of the Small House Construction in Samarinda Using the Critical Path Method (CPM). Enrichment: Journal of Management, 14(3).
Surahman, Kusumah, A., Tomby, R. S., Digital, B., & Negeri Samarinda, P. (2024). Enrichment: Journal of Management Project management planning of the small house construction in samarinda using the critical path method (CPM). In Enrichment: Journal of Management (Vol. 14, Issue 3).
Surahman, Yuni Saputri, Muhammad F. Athoya, Agung Isandarus, Ihwan H. Rabbani, Nor I. Rahmayanti, & Dwi Hidayati. (2024). House construction of time scheduling using criticalpath method (CPM) in selili district. Enrichment: Journal of Management.
TENSIX. (2025). Schedule Validation – Areas You Should Consider. Https://Tensix.Com/Schedule-Validation-Areas-You-Should-Consider/.
T. Widjajanto, “Proyek Dengan Metode CPM (Critical Path Method),” J. Manaj. Univ. Bung Hatta, vol. 2, no. September 2019, pp. 12–13, 2019.
Wijoyo, A., Reza Utama, R., Mahmud, M., Ubaydillah, F., Rahmawati, S., & Tantowi Alhabasi, M. (2023). Manajemen Proyek Sistem Informasi. 2(01). https://journal.mediapublikasi.id/index.php/bullet