Optimization of patane toraja construction implementation time using critical path method

##plugins.themes.academic_pro.article.main##

Putri Sumbung
Adila Aisyah Putri
Surahman Surahman

Abstract

One of the main challenges in the development of Patane is the lengthy implementation time due to a lack of structured and efficient time planning. This research focuses on streamlining the time needed to construct Patane, a traditional burial site of the Torajan people, by utilizing the Critical Path Method (CPM) in combination with Microsoft Project and QM for Windows software. This study aims to optimize the duration of the Patane development project by using a systematic time management approach. A descriptive quantitative methodology was used to evaluate six interconnected phases of the project, ranging from initial preparation to the final touches. The findings indicated that every activity in the project is part of the critical path, with a total float of zero, leading to an overall project timeline of 84 days. This study underscores the importance of time management tools in culturally focused construction endeavors that encompass intricate social and spiritual aspects. Implementing CPM allows for more organized, effective, and precise project planning and execution, while respecting the cultural values of the Torajan community

##plugins.themes.academic_pro.article.details##

How to Cite
Sumbung, P., Putri, A. A., & Surahman, S. (2025). Optimization of patane toraja construction implementation time using critical path method. Enrichment : Journal of Management, 15(2), 82-91. https://doi.org/10.35335/enrichment.v15i2.2264

References

Angelin, A., & Ariyanti, S. (2019). Analisis Penjadwalan Proyek New Product Development Menggunakan Metode Pert Dan Cpm. Jurnal Ilmiah Teknik Industri, 6(1), 63–70.
Apriliani, A. D. (2024). Dinamika Pelaksanaan Ritual Ngaben Di Desa Adat Sampalan Tahun 2002-2022. Jurnal Intelek Insan Cendikia, 1(10), Article 10.
Astari, N. M., Subagyo, A. M., & Kusnadi, K. (2022). Perencanaan Manajemen Proyek Dengan Metode CPM (Critical Path Method) Dan Pert (Program Evaluation And Review Technique). Konstruksia, 13(1), 164. https://doi.org/10.24853/jk.13.1.164-180
Athira, N. R., Andris, D. A. M., & Khoiroh, S. M. (2021). Crashing Project Evaluation by Managing Allocation Resource and Cost using CPM-PERT and MS,Project in Nurul Hayat Mosque’s Renovation. Tibuana, 4(02), 69–82. https://doi.org/10.36456/tibuana.4.02.3770.69-82
Belferik, R., Andiyan, A., Zulkarnain, I., Munizu, M., Samosir, J. M., Afriyadi, H., Rusmiatmoko, D., Adhicandra, I., Syamil, A., Ichsan, M., & Prasetyo, A. (2023). MANAJEMEN PROYEK: Teori & Penerapannya. PT. Sonpedia Publishing Indonesia.
Dannyanti, E. (2010). Optimalisasi pelaksanaan proyek dengan metode PERT dan CPM. Semarang. Universitas Diponegoro. https://www.academia.edu/download/31412606/Optimalisasi_Pelaksanaan_Proyek_Dengan_Metode_Pert_Dan_Cpm-Jurnal(1).pdf
Daulay, M. T., Munarsih, E., Muafiqie, H., Alkadrie, S. A., Sukasmanto, Suarlin, J., & Suparman. (2022). Konsep Dasar Manajemen Proyek di Era 4.0. CV Rey Media Grafika.
Do’o, R. R. R., Maulana, R., & Sari, S. N. (2024). Analisis Penjadwalan Waktu Kerja Proyek Menggunakan Metode CPM Pada Pembangunan Proyek Gedung DPRD Kabupaten Sleman, Yogyakarta. STORAGE: Jurnal Ilmiah Teknik dan Ilmu Komputer, 3(1), 55–62. https://doi.org/10.55123/storage.v3i1.3139
Eyiah, A. K., Bondinuba, F. K., Adu-Gyamfi, L., & Liphadzi, M. (2025). Promoting Effective Management of Cultural Diversity in Multinational Construction Project Teams. Buildings, 15(5), Article 5. https://doi.org/10.3390/buildings15050659
Haq, S. A. (2025). Strategi Efektif Perencanaan dan Pengendalian Proyek Untuk Mencapai Target Tepat Waktu. https://www.researchgate.net/profile/Mia-Global-Akademia/publication/388800308_Strategi_Efektif_Perencanaan_Dan_Pengendalian_Proyek_Untuk_Mencapai_Target_Tepat_Waktu_Sajira_Ahsanul_Haq/Links/67a6d075461fb56424cdc947/Strategi-Efektif-Perencanaan-Dan-Pengendalian-Proyek-Untuk-Mencapai-Target-Tepat-Waktu-Sajira-Ahsanul-Haq.Pdf
Huda, I. F. N., & Prasinta, W. R. (2024). Perencanaan Manajemen Proyek dengan Metode Critical Path Method (CPM) dalam Pelaksanaan Program PKL di SMK Cendekia Batujajar. EKONOMIKA45 : Jurnal Ilmiah Manajemen, Ekonomi Bisnis, Kewirausahaan, 12(1), 539–550. https://doi.org/10.30640/ekonomika45.v12i1.3617
Husna, R. A., Ilmiyah, N. F., & Resti, N. C. (2022). Implementasi CPM dan PERT dalam Memprediksi Durasi serta Biaya Pembangunan Musala Al-Ikhlas di Kotawaringin Barat. Journal Focus Action of Research Mathematic (Factor M), 5(1), 97–109.
Kadang, T., Hidayah, P. W., Simarmata, K., Putri, N. A., & Krisvinus, K. (2024). Analysis of Consultant Building Project Management Using the CPM (Critical Path Method). Journal of Business Management and Economic Development, 2(03), 1169–1179. https://doi.org/10.59653/jbmed.v2i03.891
Kartini, I., Abdullah, A., Riauwati, J., Yoeliastuti, Y., Tannady, H., Khasanah, K., Batubara, H. C., Kamisi, H. L., Liana, W., & Purbaningsih, Y. (2022). Manajemen Proyek. Cendikia Mulia Mandiri.
Mar’aini, M., & Akbar, Y. R. (2022). Penentuan jalur kritis untuk manajemen proyek (studi kasus pembangunan Jalan Selensen-Kota Baru-Bagan Jaya). Jurnal Pustaka Manajemen (Pusat Akses Kajian Manajemen), 2(1), 6–13. https://doi.org/10.55382/jurnalpustakamanajemen.v2i1.184
Markus, F. (2022). Kekerabatan Orang Toraja Kristen-Islam Berdasarkan Nilai Kultural Tongkonan Dan Falsafah Misa’Kada Dipotuo, Pantan Kada Dipomate. ARUMBAE: Jurnal Ilmiah Teologi Dan Studi Agama, 4(2), 190–203.
Milkia, M. (2023). Teologi dan Ketorajaan: Identitas Ketorajaan dari Perspektif Generasi Z Diaspora di Gereja Toraja Jemaat Gideon Tanjung Redeb Klasis Kaltara Berau [PhD Thesis, Institut Agama Kristen Negeri (IAKN) Toraja]. http://digilib-iakntoraja.ac.id/id/eprint/748
Muhammad, A., Kurniawan, B., Mufidah, A. P., La Dai, L. D. M. B., & Pakarbudi, A. (2021). Analisa Jalur Kritis Pada Penjadwalan Proyek Pengembangan Sistem Informasi Menggunakan Teknik Critical Path Method (CPM)(Studi Kasus: PT. XYZ). Prosiding Seminar Nasional Sains Dan Teknologi Terapan, 9(1), 538–547. http://ejurnal.itats.ac.id/sntekpan/article/view/2279
Perdana, M. A., & Sari, R. P. (2022). Optimalisasi Waktu Pelaksanaan Proyek Konstruksi Rumah Tinggal Menggunakan Metode CPM (Critical Path Method) dan PERT (Program Evaluation and Review Technique). Jurnal Media Teknik dan Sistem Industri, 6(2), 116. https://doi.org/10.35194/jmtsi.v6i2.1944
Pernandes, P., Puri, P. A., & Nurhasanah, S. (2024). Implementation of CPM and PERT Method in Canteen Development Project CV Super Makmur. West Science Business and Management, 2(01), 179–193. https://doi.org/10.58812/wsbm.v2i01.702
Rembulan, G. D., & Yuhao, S. (2023). Penerapan Metode CPM dan PERT Pada Proyek Konstruksi Gereja Kemah Tabernake PIK 2 Jakarta Utara. Journal Of Industrial and Manufacture Engineering, 7(2), 147–160.
Resti, R., Burchanuddin, A., & Bahri, S. (2024). Relasi Kekerabatan Masyarakat Toraja Dalam Pelaksanaan Upacara Adat Rambu Solo’ Kecamatan Rantetayo Kabupaten Tana Toraja. Jurnal Sosiologi Kontemporer, 4(2), Article 2. https://doi.org/10.56326/jsk.v4i2.4864
Saputra, I. H., Erina, Y., & Rodhi, N. N. (2024a). Analisis Pengendalian Waktu dan Biaya Proyek Konstruksi Dengan Metode CPM (Critical Path Method). Innovative: Journal Of Social Science Research, 4(6), 7797–7807. https://doi.org/10.31004/innovative.v4i6.17179
Saputra, I. H., Erina, Y., & Rodhi, N. N. (2024b). Analisis Pengendalian Waktu dan Biaya Proyek Konstruksi Dengan Metode CPM (Critical Path Method). Innovative: Journal Of Social Science Research, 4(6), Article 6. https://doi.org/10.31004/innovative.v4i6.17179
Sarunan, A. M. (2023). Perancangan Kawasan Seni dan Budaya Toraja di Toraja Utara dengan Pendekatan Arsitektur Regionalisme: Acuan Perancangan [PhD Thesis, Universitas Fajar]. https://repository.unifa.ac.id/id/eprint/1474/
Sebastian, D., & Jin, O. F. (2025). Penyebab dan Tindakan Mitigasi Pembengkakan Biaya Pada Proyek Konstruksi. Jurnal Media Teknik Sipil, 23(1), 33–42.
Sudirman, S., Kondolayuk, M. L., Sriwahyuningrum, A., Setiawan, J., Tandirerung, W. Y., Rahmi, S., Indrawati, F., Fittriya, N. L., Aziza, N., Wardhana, A., & Hasanah, T. (2023). Metodologi Penelitian 1. https://www.researchgate.net/publication/371988490_Metodologi_Penelitian_1_Deskriptif_Kuantitatif
Sugiyarto, S., Qomariyah, S., & Hamzah, F. (2013). Analisis Network Planning Dengan CPM (Critical Path Method) Dalam Rangka Efisiensi Waktu Dan Biaya Proyek. Matriks Teknik Sipil, 1(4), Article 4. https://doi.org/10.20961/mateksi.v1i4.37494
Surahman, S., Kusumah, A., Tiara, Tomby, R. S., & Nurmaulida. (2024). Project management planning of the small house construction in samarinda using the critical path method (CPM). https://doi.org/10.35335/enrichment.v14i3.1939
Surahman, S., Saputri, Y., Athoya, M. F., Rabbani, I. H., Rahmayanti, N. I., & Hidayati, D. (2024). House construction of time scheduling using criticalpath method (CPM) in selili district. Enrichment : Journal of Management, 14(2), Article 2. https://doi.org/10.35335/enrichment.v14i2.1897
Utomo, G., Hendriyani, I., & Aida, S. N. (2020). Evaluasi Pelaksanaan Proyek Drainase Dengan Metode CPM Dan PERT: Drainage Project Implementation Evaluation With The CPM And PERT Method. Media Ilmiah Teknik Sipil, 9(1), 44–52. https://doi.org/10.33084/mits.v9i1.1884
Zunaidah, U., Kawuryan, R., Prasetyo, D. R., Aditya, R., & Salsabila, S. N. (n.d.). Construction management analysis of time management in residential house construction of samarinda. 2.